Electric Line Extension

Anaheim Public Utilities is extending underground electrical circuits to provide additional capacity to Central and South Anaheim for improved reliability. 

Active Line Extension Projects:



Platinum Triangle Electric Line Extension

  • 6.6 miles of 69kV and 12kV underground power lines and will provide much needed operational flexibility of the electric system towards Platinum Triangle.
  • Project ViewFinder - project number 1909.
  • Estimated Construction Schedule: Winter 2017 – Fall 2020

Cerritos Avenue - Facing East

Cerritos Avenue

Contact Us

  1. Electrical Engineering


    Email Electrical Engineering

    Anaheim Public Utilities Electrical Engineering


    Anaheim West Tower
    201 South Anaheim Boulevard
    7th Floor
    Anaheim, CA 92805

    Phone: 714-765-5156

    Hours


    Monday - Friday
    8 a.m. - 5 -p.m.

    Directory

Wanda Electric Line Extension – Phase 1

  • 1.5 miles of 12kV underground power lines in existing/new electrical duct bank. The project will provide additional operational flexibility and improve electric systems reliability in the surrounding area.
  • Project ViewFinder - project number 2399.
  • Estimated Construction Schedule: Spring 2019 – Fall 2020

Manchester Electric Line Extension

  • 0.25 miles of 12kV underground power lines along Manchester Avenue and Disney Way.
  • Project ViewFinder - project number 2982.
  • Estimated Construction Schedule: Summer 2019 – Fall 2020

Planned Line Extension Projects:



Wanda Electric Line Extension – Phase 2

  • This project consists of installing 1.5 miles of 12kV underground power lines along Claudina Street and Ball Road.
  • Estimated Construction Schedule: Summer 2021 – Summer 2022
Project Contact:

Jason Rilloraza, jrilloraza@anaheim.net