Platinum Triangle Line Extension

Anaheim Public Utilities is extending underground electrical circuits to provide additional capacity to Central and South Anaheim for improved reliability. This project consists of installing 6.6 miles of underground power lines (3.25 miles of 69KV and 3.35 miles of 12KV) which also provides much needed operational flexibility of the electric system.

Platinum Triangle Electric Line Extension

Estimated Construction Schedule

December 2017 – Construction Starts
March 2019 – Construction Complete